Heaven 11: new-build, modern villa in La Zagaleta, Benahavís

Case Study:

A large and luxurious contemporary residence, built on a large plot with stunning Mediterranean views, just under the top ridge of one of the most high-end urbanisations in Europe, La Zagaleta. The design features lots of light-filled living space, a cutting-edge kitchen, nine en-suite bedrooms, including a stunning master suite, and a whole entertainment floor under the landscaped garden with indoor heated infinity pool, fitness suite, cinema, wine cellar, and garage fit for a car collection.

What TM did:

We were asked by an existing client, with whom we have undertaken several building projects, to source land opportunities anywhere in premium areas of Marbella for new developments.

After locating several opportunities, we decided to focus on La Zagaleta, given the shortage of new properties coming to the market in the urbanization. A fantastic plot became available and the client seized the chance to buy it, as it has 270-degree views of the coastline, all-day sunshine, and is conveniently located next to the north security entrance.

We have assisted the client with the selection of the architect and builder, and once the license was obtained from Benahavís Town Hall, building work has now begun. Terra Meridiana has been selected as the exclusive sales agent to market the property, the ultra modern villa for sale in la Zagaleta, The Heaven 11.

All case studies Ref: TMNV18184
New-build, ultra-modern villa for sale in La Zagaleta, Benahavís
Beds:
9
Baths:
9
Pool:
Private
Garden:
Private
Garage:
Private
Orientation:
South facing
Plot:
5,044m²
Build:
2,320m², 328m² terraces, over three floors
Status: Completed and fully furnished autumn 2016, available for sale: click here


Completed: Heaven 11 is within your reach! 31-01-2017

Decorated throughout with subtle elegance in natural tones and furnished with supremely comfortable designer pieces, Heaven 11 has now been fully finished and is ready to be lived in. The only things the new owner will need to bring are clothing to fill its ample walk-in wardrobes, wines to stock the shelves of its cellar […]

View all pictures

Stage 1: Laying the foundations 14-01-2017

Work began on the construction of Heaven 11 at the start of 2015. We started by clearing the site, moving earth, and building a series of stone-clad retaining walls to reach the desired elevation above the lower street level. This allowed us to create a flat, level base for the foundations. The next step was […]

View all pictures

Stage 2: Building the basement

Once the foundations were in place, we began to build the perimeter and interior walls of the basement level, which will be the entertainment hub of the house, once completed. The ramp in the foreground of the images leads down to the garage; the box in the centre will house machine rooms, the sauna, steam […]

View all pictures

Stage 3: Building the entrance level and first floor

Work continues with the construction of the entrance level, which will contain the living rooms, dining room, kitchen, and two bedroom suites, as well as the pillars which will support the roof over the first floor, which will house the master bedroom suite and two additional en-suite bedrooms. Meanwhile, the basement walls are being waterproofed […]

View all pictures

Stage 4: Building the roof

With the load-bearing structure of the building now in place, the concrete formwork can come off the structure. Work starts on the roof in the area that will cover the entrance hallway and staircases, as well as the shaft for the lift. In the last image, the silhouette of the completed property can now be […]

View all pictures

Stage 5: Plastering the façade and waterproofing the terrace

Construction work on the house is now completed, so plastering of the external walls has begun. At the same time, the terraces surrounding the outdoor pool have been waterproofed, as these areas will eventually be grassed over, and the pergola that will house the chill-out area and bar next to the jacuzzi has also been […]

View all pictures

Stage 6: Finishing the façade, terraces, and swimming pools

The façade is now almost completed, with just the pillars for the upper floor terrace and the pergola still to be plastered. Meanwhile, a concrete screed has been laid over the waterproof layer, both on the terraces and in the outdoor and indoor pools, prior to putting down the final finished surfaces.

View all pictures

Stage 7: Laying the terrace surfaces and building the retaining walls

Now that the last remaining elements of the façade have been finished, with just the pergola for the chill out area by the jacuzzi to complete, work turns to laying the tiled surfaces of the extensive outdoor terraces around the pool. At the same time, the retaining walls are being filled in to provide areas […]

View all pictures

Stage 8: Preparing the plot and terraces for landscaping

Work continues on the preparing the plot and finishing the terrace areas at Heaven 11. The extensive retaining walls are now almost entirely clad with stone, the driveway leading to the garage is close to completion, the chill-out area by the outdoor jacuzzi looks ready to receive a sofa or two, and the terrace surfaces […]

View all pictures

Stage 9: Finishing the terraces and fitting out the interior

There’s plenty of images of Heaven 11 this month, as there has been lots of progress on the project in the last few weeks. The retaining walls are now completed, the interior is really beginning to take shape — with floors laid and framing for doors and windows being installed — and the pools indoor […]

View all pictures

Stage 10: Finishing the interior and fitting out the pools

Work continues to advance smoothly at Heaven 11, with the exterior of the property now being landscaped with mature trees and borders planted. Inside, the glazing has now been fitted; you can really appreciate how light and spacious the property is and also how the design features breathtaking views from every room and from the […]

View all pictures

Stage 11: Work continues inside and out

Both the indoor and outdoor swimming pools and jacuzzis at Heaven 11 are now almost complete, with the large-format tiles cut and fitted to the interior. Outside the villa, landscaping work continues with the garden around the pool being prepared to lay lawn. Inside, work continues on finishing the property: the lift has now been […]

View all pictures

State 12: Getting closer to completion

The swimming pools and jacuzzis have been finished and filled, the lawns have been laid, the trees and borders planted, and the driveway, entrance pathway, and terraces have all been completed. From the outside, once the builders remove their equipment, Heaven 11 looks almost ready to live in. Indoors, the glass guardrail and balustrade for […]

View all pictures

Stage 13: The finishing touches

Although the furniture and decoration that will really make the property feel like home has not yet arrived and the last few light fitments and other little details are still to be fitted, Heaven 11 is now ready to be lived in. Over the last couple of months since the previous update, the spa area […]

View all pictures